Weekly Meeting #04
Date |
|
|---|
1. Participants & Attendance
Name | Company | Role |
|---|---|---|
Tomi Toivonen | Valio | Pricing Manager |
Emmo Kaipia | Valio | Project Manager |
Teemu Salonen | Valio | Pricing Analyst |
Alain Becker | Pearson Ham Group | Operation Manager |
Christiaan Van Eden | Pearson Ham Group | Consultant |
Omar Bendada | Ben Consulting Services | Business Analyst |
Sofia Simaria | Ben Consulting Services | Proxy Product Owner |
2. Project Updates
Weekly re occurring meeting set -up completed
Build phase begins next week
Sprint planning taking place 10/11 June - completed
Sprint planning
Scope Content Document - 85% complete
Aim is to have this completed / signed off by
Initial review of the content has taken place
Comments have been added and BCS are updating
Further reviews being actioned as required, with key people advised
There has been some initial scope creep. The work will be reviewed and sized
Backlog
Start of drafting backlog - completed but this is a ‘live document’ and may change as we progress the build
User Stories need to be linked to the SCD - in progress
Business SME’s meeting for technical set up and invites sent
Attendees agreed. with some invitees removed
Action Tracker site - completed (Replacing Project Action Tracker, Excel file)
This has been created and will become the place to view all project actions. It will list due dates, who is assigned etc. for both BCS and Valio
Zilliant Platform Access
Env access for CPQ is all good for BCS
Integrations
Outstanding data mapping questions needs answering
3. Follow-up on Actions
|
|
4. Project Progress Overview
Workstream / Deliverable | Status | Key Notes |
|---|---|---|
Functional Workshops | DONE | |
Environment Setup | DONE | |
SCD writing | IN PROGRESS | |
Backlog | IN PROGRESS | |
Technical Doc Spec | IN PROGRESS |
Legend: DONE | IN PROGRESS | NOT STARTED | AT RISK
5. Issues & Risks
Topic | Impact | Owner | Next Step |
|---|---|---|---|
MSP Access | Build will be delayed if not provided by | Emails have been sent and work is being actioned to finalise |
6. Decisions
7. Next Steps / New Actions
Task | Responsible | Due Date | Planned Status |
|---|---|---|---|
8. Open Questions / Topics discussed during meeting
9. Project Timeline

Phase / | Target Dates | Status | |
|---|---|---|---|
Design Design | Workshop | May – June | 🟢 |
Environment Setup | May – June | 🟢 | |
Build | CPQ Implementation | June – September | 🟢 |
Data Management | June – September | 🟢 | |
System Interface | June - September | 🟢 | |
Deployment | June - September | 🟢 | |
UAT | Bug correction | October | 🟢 |
Training Session | October | 🟢 | |
Go-Live Prep | November | 🟢 |