Weekly Meeting #05
Date |
|
|---|
1. Participants & Attendance
Name | Company | Role |
|---|---|---|
Tomi Toivonen | Valio | Pricing Manager |
Emmo Kaipia | Valio | Project Manager |
Teemu Salonen | Valio | Pricing Analyst |
Alain Becker | Pearson Ham Group | Operation Manager |
Christiaan Van Eden | Pearson Ham Group | Consultant |
Omar Bendada | Ben Consulting Services | Business Analyst |
Sofia Simaria | Ben Consulting Services | Proxy Product Owner |
2. Project Updates
Scope Content Document - 90% complete
Aim is to have this completed / signed off by
There has been some initial scope creep. The work will be reviewed and sized for reference
Backlog
Start of drafting backlog - completed
User Stories need to be linked to the SCD - Completed
Action Tracker site - completed (Replacing Project Action Tracker, Excel file)
Environment CPQ
Reset access outstanding - working to resolve by
Integrations
Outstanding data mapping questions needs answering - Check with Sofia
Price Manager Tables
Ask Tomi to download and share all Price Manager tables that are relevant for CPQ (master data, locally managed data, price lists, PIQ guidance, output tables) - requested via Teams
Missing tables being set to Sofia
3. Follow-up on Actions
|
|
4. Project Progress Overview
Workstream / Deliverable | Status | Key Notes |
|---|---|---|
Functional Workshops | DONE | |
Environment Setup | DONE | |
SCD writing | IN PROGRESS | Changes being reflected as comments received from Tomi & Teemu |
Backlog | DONE | |
Technical Doc Spec | IN PROGRESS |
Legend: DONE | IN PROGRESS | NOT STARTED | AT RISK
5. Issues & Risks
Issues | Impact | Owner | Next Step |
|---|---|---|---|
AWS reset | Unable to reset AWS which is having an impact on build for testing new functionality | Zilliant Support | Ticket raised with Zilliant |
6. Decisions
7. Next Steps / New Actions
Task | Responsible | Due Date | Status |
|---|---|---|---|
8. Open Questions / Topics discussed during meeting
9. Project Timeline

Phase / | Target Dates | Status | |
|---|---|---|---|
Design Design | Workshop | May – June | 🟢 |
Environment Setup | May – June | 🟢 | |
Build | CPQ Implementation | June – September | 🟡 |
Data Management | June – September | 🟢 | |
System Interface | June - September | 🟢 | |
Deployment | June - September | 🟢 | |
UAT | Bug correction | October | 🟢 |
Training Session | October | 🟢 | |
Go-Live Prep | November | 🟢 |