2. Project Updates

  • Sprint 2 - End of sprint; preparing for Client review 04/08

  • CHallenging implementationtopics to be finished today

  • No Integrations have been implemeted in this sprint - Need to organise a reccurent call to discuss integration topics @a user

  • Reinforcement of the team with Jean-Baptiste and Manveer back from his recovery period will have a positive impact on Sprint 3 progress

  • Eventual impact on deployment of the implemented solution in relation to the additional sprint + SAP project delay.

image-20250801-091116.png

image-20250801-091143.png

image-20250801-091346.png

3. Project Progress Overview

Workstream / Deliverable

Status

Key Notes

Functional Workshops

DONE

Environment Setup

DONE

SCD writing

DONE

Changes being reflected in yellow

Backlog

DONE

Technical Doc Spec

DONE

Legend: DONE | IN PROGRESS | NOT STARTED | AT RISK


4. Issues & Risks

Issues

Impact

Owner

Next Step

Velocity of the delivery could impact the project progress

This is to be discussed in the end of Sprint 2 and evaluate the impact on the project

Omar

Onboarding new developer (Done)

Sprint 2 - outstanding stories not completed

Not all user stories completed due to holiday period.

Terry

US Rescheduled to the next Sprint


5. Decisions


    6. Next Steps / New Actions

    Task

    Comment / Description

    Due Date

    Status

    Open Points

    Need to be reviewed & progressed

    🟡

    Sprint

    Additional sprint may be needed

    🟡


    7. Open Questions / Topics discussed during meeting


    8. Project Timeline

    image-20250801-065734.png

    Phase /

    Target Dates

    Status

    Design

    Design

    Workshop

    May – June

    🟢

    Environment Setup

    May – June

    🟢

    Build

    CPQ Implementation

    June – September

    🟡

    Data Management

    June – September

    🟢

    System Interface

    June - September

    🟡

    Deployment

    June - September

    🟡

    UAT

    Bug correction

    October

    Training Session

    October

    Go-Live Prep

    November