Weekly Meeting #32
Date |
|
|---|
1. Participants & Attendance
Name | Company | Role |
|---|---|---|
Emmi Kaipia | Valio | Head of Business Development |
Teemu Salonen | Valio | Pricing Analyst |
Tomi Toivonen | Valio | Pricing Manager |
Omar Bendada | Ben Consulting Services | Business Analyst |
Peter Jarvis | Ben Consulting Services | Project Manager |
2. Progress Summary
Three principal outstanding issues to resolve to deliver an MVP for Soft Go-Live
BCS to implement margin calculations and summary page
Zilliant to resolve three outstanding bugs
Zilliant, supported by BCS, to get the performance of CPQ to an acceptable level
Margin calculations are ready for testing
Development for Finished Goods and Product Groups both completed this week
Basic testing at BCS has passed, but significant additional data will be required from Valio to support more detailed testing scenarios
CPQ product bugs are still outstanding
Scripts to update CPQ from Price Manager not running automatically: fix received and confirming at BCS
Date discrepancies on agreement creation, guidance retrieval and publish: fix has issues still
Cannot copy net priced items from another deal: fix fails intermittently
Performance to be addressed once functional issues are complete
Some improvements made already, but still not acceptable
Scripts have been reviewed by Zilliant technical teams and some suggestions received
Some other bugs remain, but the above lists the main headings to be addressed by 23rd Jan
3. State of Readiness for Soft Go-Live
Margin Calculations and Summary Page
Requirements are fully clear
We have tested the basic calculations at Zilliant so far as we can, based on the limited lookup data which is currently held in CPQ
Before going fully live this feature will require more extensive testing against more complete scenarios, which in turn will require more complete test data to be uploaded to CPQ; this is in hand with the Valio project team
We believe nevertheless that we can still proceed to a soft go-live with this beta version, which in itself will provide more test scenarios
Bugs With Zilliant for Resolution

Ref | Description | Status | Delivery Date |
|---|---|---|---|
VAL-598 | Valio guidance is giving wrong numbers | Immediate issue fixed and correct guidance is now retrieved from CPQ Script for updating guidance from PM to CPQ was not running on automated schedule, hence guidance in CPQ was not current Zilliant has fixed the script issue and we are running further tests to confirm it now works | 27th Jan |
VAL-644 | New net price from PM to CPQ (net price process) | Same script automation issue as 589 above | 27th Jan |
VAL-607 | CPQ and PM dates not in sync | ||
VAL-740 | Deal start and end date | Fix received as promised but it does not work consistently Seems to be a problem of dates held as date-time values, which can cause date to change between time zones, and a problem of inconsistent times applied to different date fields Bug passed back to Zilliant for resolution | tbc |
VAL-716 | Can’t set prices on lines screen | ||
VAL-749 | Can’t copy net priced items from another deal | Fix delivered as promised last week, but it seems to work very inconsistently: issue seems to be solved then it reappears Zilliant think that a script may be removing currency from agreements; have asked for assistance in isolating where this may be happening | tbc |
Performance
The principal issue is that it was taking 10-15 minutes to add a Product Group. We have implemented some suggestions from Zilliant into the relevant scripts and this has reduced to 3 minutes or less. However, Save now takes 7 minutes. We have shared our scripts with Zilliant and their technical teams have responded with some further suggestions on 21st Jan. We will investigate these suggestions next week.
Completion of MVP for Soft Go-Live
Soft go-live date remains uncertain while bugs and performance issues remain unsolved. We have escalated within Zilliant and have requested that they work with us to create a joint plan which both parties can commit to.
4. Project Timeline