Weekly Meeting #32

Date

1. Participants & Attendance

Name

Company

Role

Emmi Kaipia

Valio

Head of Business Development

Teemu Salonen

Valio

Pricing Analyst

Tomi Toivonen

Valio

Pricing Manager

Omar Bendada

Ben Consulting Services

Business Analyst

Peter Jarvis

Ben Consulting Services

Project Manager


2. Progress Summary

  • Three principal outstanding issues to resolve to deliver an MVP for Soft Go-Live

    • BCS to implement margin calculations and summary page

    • Zilliant to resolve three outstanding bugs

    • Zilliant, supported by BCS, to get the performance of CPQ to an acceptable level

  • Margin calculations are ready for testing

    • Development for Finished Goods and Product Groups both completed this week

    • Basic testing at BCS has passed, but significant additional data will be required from Valio to support more detailed testing scenarios

  • CPQ product bugs are still outstanding

    • Scripts to update CPQ from Price Manager not running automatically: fix received and confirming at BCS

    • Date discrepancies on agreement creation, guidance retrieval and publish: fix has issues still

    • Cannot copy net priced items from another deal: fix fails intermittently

  • Performance to be addressed once functional issues are complete

    • Some improvements made already, but still not acceptable

    • Scripts have been reviewed by Zilliant technical teams and some suggestions received

  • Some other bugs remain, but the above lists the main headings to be addressed by 23rd Jan

3. State of Readiness for Soft Go-Live

Margin Calculations and Summary Page

  • Requirements are fully clear

  • We have tested the basic calculations at Zilliant so far as we can, based on the limited lookup data which is currently held in CPQ

  • Before going fully live this feature will require more extensive testing against more complete scenarios, which in turn will require more complete test data to be uploaded to CPQ; this is in hand with the Valio project team

  • We believe nevertheless that we can still proceed to a soft go-live with this beta version, which in itself will provide more test scenarios

Bugs With Zilliant for Resolution

image-20260122-151049.png

Ref

Description

Status

Delivery Date

VAL-598

Valio guidance is giving wrong numbers

Immediate issue fixed and correct guidance is now retrieved from CPQ

Script for updating guidance from PM to CPQ was not running on automated schedule, hence guidance in CPQ was not current

Zilliant has fixed the script issue and we are running further tests to confirm it now works

27th Jan

VAL-644

New net price from PM to CPQ (net price process)

Same script automation issue as 589 above

27th Jan

VAL-607

CPQ and PM dates not in sync

VAL-740

Deal start and end date

Fix received as promised but it does not work consistently

Seems to be a problem of dates held as date-time values, which can cause date to change between time zones, and a problem of inconsistent times applied to different date fields

Bug passed back to Zilliant for resolution

tbc

VAL-716

Can’t set prices on lines screen

VAL-749

Can’t copy net priced items from another deal

Fix delivered as promised last week, but it seems to work very inconsistently: issue seems to be solved then it reappears

Zilliant think that a script may be removing currency from agreements; have asked for assistance in isolating where this may be happening

tbc

Performance

The principal issue is that it was taking 10-15 minutes to add a Product Group. We have implemented some suggestions from Zilliant into the relevant scripts and this has reduced to 3 minutes or less. However, Save now takes 7 minutes. We have shared our scripts with Zilliant and their technical teams have responded with some further suggestions on 21st Jan. We will investigate these suggestions next week.

Completion of MVP for Soft Go-Live

Soft go-live date remains uncertain while bugs and performance issues remain unsolved. We have escalated within Zilliant and have requested that they work with us to create a joint plan which both parties can commit to.

4. Project Timeline