Weekly Meeting #33

Date

1. Participants & Attendance

Name

Company

Role

Emmi Kaipia

Valio

Head of Business Development

Teemu Salonen

Valio

Pricing Analyst

Tomi Toivonen

Valio

Pricing Manager

Omar Bendada

Ben Consulting Services

Business Analyst

Peter Jarvis

Ben Consulting Services

Project Manager


2. Progress Summary

  • Three principal outstanding issues to resolve to deliver an MVP for Soft Go-Live

    • BCS to implement margin calculations and summary page

    • Zilliant to resolve three outstanding bugs

    • Zilliant, supported by BCS, to get the performance of CPQ to an acceptable level

  • Margin calculations are in testing and summary page to complete today

    • Basic testing at BCS has passed, but significant additional data will be required from Valio to support more detailed testing scenarios

    • Summary page is in progress and expected to be ready for testing from Monday

  • CPQ product bugs are still outstanding

    • Scripts to update CPQ from Price Manager not running automatically: fix worked briefly at BCS but now does not and investigating further with Zilliant

    • Date discrepancies on agreement creation, guidance retrieval and publish: fix to be delivered for testing on Monday

    • Cannot copy net priced items from another deal: fix tested at BCS and passed to Valio to confirm

  • Performance to be addressed once functional issues are complete

    • Some improvements made already, but still not acceptable

    • Scripts have been reviewed by Zilliant technical teams and some suggestions received

    • Zilliant believe that the main performance issue is the number of API calls made to Price Manager, and we are working with them to reduce the number of calls which are required

    • For this reason, it is not believed that increasing the CPU power of the server would have much impact on performance at this stage

  • Some other bugs remain, but the above lists the main headings to be addressed before Soft Go-Live

3. State of Readiness for Soft Go-Live

Margin Calculations and Summary Page

  • Calculations for both Finished Goods and Product Groups have been tested at Zilliant so far as we can, based on the limited lookup data which was available in CPQ

  • Before going fully live this feature will require more extensive testing against more complete scenarios, which in turn will require more complete test data to be uploaded to CPQ; this is in hand with the Valio project team

  • We believe nevertheless that we can still proceed to a soft go-live with this beta version, which in itself will provide more test scenarios

Bugs With Zilliant for Resolution

image-20260129-151243.png

Ref

Description

Status

Delivery Date

VAL-598

Valio guidance is giving wrong numbers

Numbers are not being updated because automated scripts are not running as they should.

We have implemented detailed logging in the code, which has captured no data at all. This suggests to us that the jobs are not even being kicked off and that something is wrong with the mechanism that makes the scripts run every two minutes.

We will be further investigating the set-up of this mechanism with Zilliant when we meet this morning.

tbc

VAL-644

New net price from PM to CPQ (net price process)

Same script automation issue as 589 above

tbc

VAL-785

Product mass replacement | can't find added products

Same script automation issue as 589 above

tbc

VAL-740

Deal start and end date

Diagnosed as a problem of dates held as date-time values, which can cause date to change between time zones. Fix in progress.

02-Feb

VAL-749

Can’t copy net priced items from another deal

With Valio for validation

VAL-804

Revision problem -> can't create revision (net price update)

Closed. Same underlying issue as VAL-749

Performance

Initial analysis is that the main cause of poor performance is the number of API calls which are made to Price Manager from CPQ. We are together investigating how we can best bundle up and minimise those calls, while still being able to display relevant and current information to the user in a timely manner. We have had some initial discussions and expect to progress these options next week.

Completion of MVP for Soft Go-Live

Soft go-live date remains uncertain while bugs and performance issues remain unsolved. We are now working more efficiently with Zilliant to resolve these issues, though performance work in particular is iterative and will complete when performance is at an acceptable level. We are working with Zilliant to obtain an outline plan for performance work and a target date which we can commit to.

4. Status of Changes

We now have a response from Valio to BCS’s list of changes, and discussions are ongoing.

5. Project Timeline